Q3.
The primary objective of project scheduling is:
Correct Answer:
B
Scheduling defines activity sequences and timelines for projects.
Q4.
In CPM, the critical path is:
Correct Answer:
B
Critical path determines the minimum project duration.
Q5.
What is crashing in project management?
Correct Answer:
A
Crashing reduces total project time by adding resources.
Q7.
PERT stands for:
Correct Answer:
A
PERT is a method for project time analysis.
Q8.
The slack in a project activity is:
Correct Answer:
A
Slack is the allowable delay without affecting overall project time.
Q9.
In project cost management, indirect costs are:
Correct Answer:
A
Indirect costs include overheads and administrative expenses.
Q11.
Lead time in project management indicates:
Correct Answer:
A
Lead time allows overlap of dependent tasks.
Q12.
Earned Value Management (EVM) integrates:
Correct Answer:
A
EVM evaluates project performance and progress.
Q13.
Gantt charts primarily represent:
Correct Answer:
A
Gantt charts depict project schedules.
Q14.
In risk management, mitigation means:
Correct Answer:
A
Mitigation aims to reduce adverse risk effects.
Q16.
Work Breakdown Structure (WBS) helps in:
Correct Answer:
A
WBS breaks down projects into task hierarchies.
Q17.
Crashing a project increases:
Correct Answer:
A
Crashing reduces duration but may increase cost.
Q18.
The term "Float" or "Slack" indicates:
Correct Answer:
A
Float allows schedule flexibility.
Q20.
What is the main purpose of tender documents?
Correct Answer:
A
Tender documents provide contract scope for bidding.
Q21.
A bar chart shows:
Correct Answer:
A
Bar charts visualize scheduling.
Q22.
The critical path is the path which:
Correct Answer:
A
Critical path determines minimum project duration.
Q23.
EVM variance analysis helps to determine:
Correct Answer:
A
EV variance shows if project is on schedule and budget.
Q24.
Critical Chain Project Management mainly focuses on:
Correct Answer:
A
Critical Chain manages resources and reduces project duration.
Q25.
In resource leveling, the aim is to:
Correct Answer:
A
Resource leveling balances demands.
Q26.
Which contract type has fixed price?
Correct Answer:
A
Lump sum contracts specify fixed total price.
Q28.
Project crashing reduces project duration by:
Correct Answer:
A
Crashing allocates more resources.
Q29.
Buffer in project management serves as:
Correct Answer:
A
Buffers mitigate risks and delays.
Q33.
Cost control in construction project involves:
Correct Answer:
A
Cost control ensures project cost adherence.
Q34.
Integrated project management includes:
Correct Answer:
A
Integrated management covers all aspects.
Q35.
Project risk management aims to:
Correct Answer:
A
Risk management proactively handles uncertainties.
Q37.
Construction productivity can be improved by:
Correct Answer:
A
Planning and tech boost productivity.
Q38.
Lead time is the:
Correct Answer:
A
Lead time includes total activity time.
Q39.
What is the function of a project monitor?
Correct Answer:
A
Monitors help track and control projects.